Case Study

Stowmarket High School

Project timescale:
16 Weeks

Stowmarket High School was our 2nd school out of 3 awarded to start on site
the scheme consisted of full Demolition and removal of all floor slab and foundations

Project Summary

  • 404.82 Tons of Scrap Metal removed from site
  • 439.14 Tons of General Waste removed from site
  • 82.51 Tons of Wood removed from site
  • 45.16 Tons of Asbestos removed from site
  • 13,719.92 Tons of Hardcore removed from site
  • 21, 872L of Red Diesel used on site
  • 6543 Man hours throughout the project