This is another fantastic project to involved in with one of our biggest clients
Demolition, Asbestos Removal & scaffolding works took places throughout this phase of works
With an experienced team on site it didn’t take long for all stripping out and building splits to be undertaken
Once completed 2x 24 Ton excavators were taken to site where work commenced
5 weeks with 2 excavators and all demolition works were completed and all concrete slabs and foundations were removed
Many thanks to all involved with this project
Project Summary
- •2758.78 Tons of Hardcore Removed from site
- •564.27 Tons of Concrete Removed from site
- •1.44 Tons of Asbestos Removed from site
- •5.9 Tons of Plasterboard Removed from site
- •179.34 Tons of General Waste Removed from site
- •74.06 Tons of Scrap Metal Removed from site
- •18.46 Tons of Woof Removed from site







