East Point Academy

Lowestoft, Suffolk
3602 Tonnes Total Waste Removed
Timescale: 7 Weeks

This was another fantastic project for all of our divisions to be involved in, for one of our biggest clients.

Demolition, asbestos removal and scaffolding works took place throughout this phase of works.. With an experienced team on site, it didn’t take long for all stripping out and building splits to be undertaken.

Once completed, 2 x 24 ton excavators were taken onto site where work commenced. 5 weeks with 2 excavators and all demolition works were completed and all concrete slabs and foundations were removed.

  • 2758.78 tons of hardcore removed from site
  • 564.27 tons of concrete removed from site
  • 1.44 tons of asbestos removed from site
  • 5.9 tons of plasterboard removed from site
  • 179.34 tons of general waste removed from site
  • 74.06 tons of scrap metal removed from site
  • 18.46 tons of wood removed from site
01953 608050 | mail@angliandemo.co.uk